We start the week with good news and provide a comprehensive list of work we have done during the quarantine period:

– Recuperators (Komfovent Domekt) are already installed in buildings A and B.
– Outdoor decor installation works – 46 percent;
– In buildings A and B, the volume of installation of elevators (Orona) is 50 percent;
– Ceiling installation works in corridors of buildings A and B – 50%,
– In the corridors of buildings A and B, wall and sound insulation works – 100%;
– Concreting of the underground car park floor was started;
– External engineering network installation works – 100 percent;
– Installation of heating points – 90 percent.