Construction Progress
CONCRETE WORKS - overlapping of the 5 floor. flooring 100% reinforcement is completely connected in the buildings A and B, the bottom reinforcement in the building C.

WALL BRICKWORKS – currently being carried out on the 4th floor, 72% of completion has been achieved in all the buildings: the building A – 50%, the building B – 90%, the building D – 70%, the building C – 80%.
PLUMBING are made in all 4 buildings. The risers of cold water supply, hot water circulation and heating are mounted.